Resource planning

Resource planning is the practice of matching the people you have, and the hours they can work, to the client work you expect to deliver over the coming weeks or months.

Why it matters for agencies

Without a plan, agencies discover a shortage when the work is already late, or discover too much spare time when the money has already been spent. A plan turns hiring, contractors and saying no to work into decisions made early.

How to do it or work it out

List each person's available hours for the period, after leave and public holidays, and reduce them to billable capacity using a realistic utilisation target for their role.

List the demand: confirmed work at full weight and likely work at a discount. Compare supply and demand week by week, and decide what to do about any gap.

Plan in weeks for the next quarter and in months beyond that. Detail further out is false precision, because projects start late and scopes change. Revisit the plan whenever leave is approved or a project moves.

Plan by skill as well as in total. Five people with spare hours do not help if the shortage is in development and the spare hours are in design. Do the supply and demand sum once for each skill, and only then add them up.

When a gap shows, you have a short list of moves, roughly from cheapest to dearest: move a start date, change who does what within the team, borrow time from a quieter project, bring in a contractor, hire, or decline the work. Writing the gap down in hours, and the move you chose, lets you check a month later whether it worked.

Resource planning and capacity planning overlap, and people use the words loosely. In this glossary, capacity planning is the supply side, how many billable hours the team has, and resource planning is the match between that supply and named work, person by person and week by week.

A worked example

Five designers each have 30 billable hours a week, so supply is 150. Confirmed work is 140 hours and a likely project adds 25, weighted at half, which is 12.5. Demand is 152.5 hours against 150 of supply, a small gap you can cover with a contractor or by moving a start date. If the likely project is lost, demand falls to 140 hours against 150 of supply, leaving 10 spare hours for internal work or a pitch. Without the weighting, you might have hired a contractor you did not need. Now suppose the team is not all designers, and the same 150 hours of supply are 100 of design and 50 of development, against demand of 90 design hours and 62.5 development hours. In total the gap is small, but development is 12.5 hours short while design has 10 spare. Moving some design time onto production work, or a development contractor for two or three weeks, closes it.

Common mistakes

  • Planning against contracted hours. Leave, holidays, meetings and admin are not available for client work, so the plan overbooks everyone.
  • Treating likely work as confirmed. A pipeline of maybes at full weight makes the team look short of people when it may not be. The opposite error is planning only in total hours: skills and time zones decide who can do which work, so a balanced total can hide a real shortage.
  • Planning once. A plan that is not revisited is out of date within weeks, and people stop trusting it.