Retainer burndown

A retainer burndown is a line showing how many hours of a retainer are left at the end of each week, drawn against a straight line that would use them up exactly at month end.

Why it matters for agencies

A single "hours used" figure does not say whether the month is on course. The burndown puts the hours used next to the time gone, so an account lead can see on a Monday whether the hours will last, and talk to the client while there is still time to choose what to do.

How to do it or work it out

Start with the hours available: the monthly allowance plus any hours carried in from the month before. This is the top of the line.

At the end of each week, subtract the hours logged so far from the hours available. That is the actual line.

Work out the even-pace line: hours available multiplied by the days still to come, divided by the days in the month. The gap between the two lines is how far ahead or behind an even pace the account is.

A worked example

A retainer has 34 hours available in a 31-day month: 30 allowed plus 4 carried in. After week 1 the team has logged 8 hours, so 26 are left, against an even-pace figure of 26.3 (34 times 24 over 31), a gap of 0.3 hours. After week 3, 24 hours are used and 10 are left, against 11.0 on an even pace, so the account is 1 hour ahead of pace. After week 4, 30 are used and 4 are left, against 3.3, so the account is slightly behind pace and will finish the month with 4 unused hours. Whether those hours carry over depends on the agreement.

Common mistakes

  • Starting the line at the allowance when hours carry in. If 4 hours came in, the line starts at 34, or a carried balance looks like an overrun.
  • Treating the even-pace line as a target. Real work is lumpy, so use the gap to ask a question, not to judge the team.
  • Showing the chart with no explanation. The client wants one sentence on what drove the hours and what comes next.